An interactive look at major milestones between today and property closing, with a look ahead towards permitting, construction, and opening day for 105 2nd St, Oakland.
These figures follow Scheme B (Balanced — 5 indoor courts, 1 outdoor court, 3 classrooms) from the Task A concept test fit, plus the Task B diligence budget. They are order-of-magnitude estimates pending structural pricing and subcontractor bids — not a final budget or a firm schedule.
Scheme A (4 courts, minimal modifications) would likely trim a few weeks off this schedule given its lighter scope of work. Scheme C (6 courts, full second-floor buildout with two column moves and a new elevated roof) would likely add a few months, mainly to design and construction — the overall milestone sequence would stay the same either way.